Pennant Hills Park Netball
The reconstruction of Netball Courts 1 and 2 at Pennant Hills Park was completed in April 2024.
Works included:
- Demolition of existing courts 1 and 2
- Construction of two new netball courts
- New sandstone retaining/seating walls
- New court fencing
- New pedestrian paths
Funding for this project was provided by Hills District Netball Association.
Documents
- Concept Plan (PDF 3.3MB)
Enquiries
For enquiries please contact Zoe Cooke, Landscape Architect/Project Manager, Parks, Trees and Recreation team on 02 9847 6885.
April 2024 update
The reconstruction of Netball Courts 1 and 2 at Pennant Hills Park was completed in April 2024.
February 2024 update
Construction of netball courts 1 and 2 is nearing completion. The court surface has been prepared ready for painting, new paths have been constructed and turf has been laid.
The project is scheduled for completion on Wednesday 27 March, weather permitting.
January 2024 Update
Construction of the new sandstone retaining/seating wall is underway and concrete formwork is being set up for the court edging. Preparations are underway for new fencing to be installed to the north and east of the courts and the court surface is being prepared ready for asphalting which is scheduled to take place in February.
December 2023 Update
Reconstruction of courts 1 and 2 has commenced. Demolition of the existing court surface and log retaining wall is now complete and the basbase is being prepared for the new court surfacing.