Westleigh Park image gallery
What we've done so far
- 2000
Hornsby Leisure Strategic Plan - Stage 2 - 2002
Hornsby Leisure Strategic Plan - Stage 3 - 2006
Hornsby Sports Facility Strategy - 2011
Northern Sydney Regional Organisation of Councils – Regional Sportsground Strategy Review - 2016
Hornsby Shire Council buys the land from Sydney Water
Active Living Hornsby Strategy - 2017
Northern Sydney Regional Organisation of Councils – Regional Sportsground Strategy Review - 2018
Adoption of Sportsground Strategy
Hornsby Sportsground Strategy
North District Plan – Connecting Communities - 2019
Development of Westleigh Park Master Plan - 2020
Hornsby Local Strategic Planning Statement - 21 Apr to 16 Jun 2021
Exhibition of draft Master Plan - 14 Jul 2021
Adoption of draft Master Plan deferred - Mar and Jun 2022
Further community engagement - 2023
Northern Sydney Regional Organisation of Councils - Review of Supply and Demand for Sports Facilities - 13 Mar to 11 Apr 2023
Public Exhibition of revised draft Master Plan and draft Plan of Management - 14 Jun 2023
Adoption of Master Plan and Plan of Management - Jun to Sep 2023
Preparation of documentation for Development Application - 25 Sep 2023
Development Application lodged - Late 2024
Development Application determination
Anticipated commencement of procurement for construction tender (pending approval of DA)