Edward Bennett Oval, Cherrybrook - Gross Pollutant Trap, Bio-filtration Basin & Stormwater Harvesting
Description of Works
The proposed works include installation of a Gross Pollutant Trap, bio-filtration basins and stormwater harvesting system. The aim of these works is to improve the ecological health of the natural water course by improving water quality and utilising stormwater for irrigating the oval.
The works are anticipated to start this financial year and take approximately 12 weeks to complete dependent on the weather.